Design management of clean energy projects from the perspective of partnering
Yubin ZHAO, Guo LI, Wenzhe TANG
Journal of Tsinghua University(Science and Technology) ›› 2025, Vol. 65 ›› Issue (1) : 115-124.
PDF(1266 KB)
PDF(1266 KB)
Design management of clean energy projects from the perspective of partnering
Objective: Developing clean energy is crucial for achieving China's "double carbon" goals, prompting active investment in clean energy projects across the country. However, these projects face a complex external environment with many stakeholders, which makes large-scale grid integration challenging. Moreover, existing projects often suffer from issues such as insufficient energy allocation regulation, mismatched installed capacity and power demand, low economic efficiency in power transmission, and poor synergy effect among projects, mainly owing to inadequate design management. Although design management is vital in clean energy project management, a lack of research is observed from a collaborative perspective among participants. Methods: This study adopted a mixed research method that combined quantitative research and qualitative research. Quantitative data were obtained through questionnaire surveys, whereas qualitative data were obtained through semistructured interviews and case studies. Respondents included experienced professionals in clean energy project construction, such as owners, designers, suppliers, constructors, and supervisors. Herein, data analysis involved descriptive statistics, mean ranking analysis, difference testing, cluster analysis, and structural equation modeling. Results: The results show that partnering, feasibility studies, and owner's design management positively impact project performance through two paths: (1) partnering → feasibility study → design performance → project performance and (2) partnering → owner's design management → (feasibility study) → design performance → project performance. During the feasibility study, designers should deeply analyze the supply and demand of the clean energy power market, identify internal and cross-regional power consumption objects, and completely master the basic information of the design. They should rationally select sites, strengthen technical scheme demonstrations, fully consider site and surrounding area constraints, reasonably plan project resettlement and environmental protection, and ensure the project's economic feasibility. In the design process, owners should fully understand national and regional energy policies, deepen their understanding of the project objectives and design needs, and guide design development effectively. The contract should specify the design scope, depth, quality, and schedule requirements and reasonably define the responsibilities, rights, and obligations of all parties. It is crucial to establish a sound design management system, prepare a clear design schedule, and dynamically adjust the schedule as required. Implementing a sound design review, change, and optimization process, identifying design risks, and establishing corresponding control mechanisms are also essential. Developing operable design assessment indicators, reasonable reward and punishment measures, and a design interface management mechanism for stakeholders, along with actively applying information technology, is recommended. Combined with a case analysis, this study offers design management suggestions. Conclusions: This study proposes and validates a design management model for clean energy projects, revealing the considerable positive effects and pathways of partnering, feasibility studies, and owner's design management on project performance. Through questionnaires and interviews, this study deeply analyze the current state of the feasibility studies and design management, identifying key issues and factors to focus on in clean energy project design. The results provide theoretical and practical references for managing clean energy project design.
clean energy projects / partnering / owner's design management / feasibility study
| 1 |
杨跃斌, 曹路. 南方区域抽水蓄能电站项目前期管理实践[J]. 水电与新能源, 2015 (10): 53-57, 65.
|
| 2 |
钟敏. 水电项目前期规划问题探究[J]. 广东科技, 2012, 21 (11): 102, 110.
|
| 3 |
|
| 4 |
|
| 5 |
|
| 6 |
|
| 7 |
陈云华, 唐文哲, 王继敏, 等. 大型水电EPC项目建设管理创新与实践[M]. 北京: 中国水利水电出版社, 2020.
|
| 8 |
余自业, 唐文哲. 数字经济下水利工程建设管理创新与实践[M]. 北京: 清华大学出版社, 2022.
|
| 9 |
朱玉方. 水电项目前期工作研究[J]. 红水河, 2010, 29 (6): 79-84, 94.
|
| 10 |
李俊华. 浅谈水电项目前期工作管理[J]. 价值工程, 2013, 32 (21): 73- 74.
|
| 11 |
|
| 12 |
|
| 13 |
李凤新, 张振, 付璇, 等. 浅谈设计管理在项目运行中的重要性及体会[J]. 石化技术, 2016, 23 (2): 260.
|
| 14 |
王胜斌, 缪正建, 武文杰. 全过程工程咨询设计管理实践与绩效评价[J]. 工程技术研究, 2023, 8 (22): 171- 173.
|
| 15 |
|
| 16 |
王涛. 工程项目中业主方的设计管理研究: 以连云港项目为例[D]. 北京: 北京建筑大学, 2020.
WANG T. Research on the design management process of the owner of construction projects: Take a project as an example[D]. Beijing: Beijing University of Civil Engineering and Architecture, 2020. (in Chinese)
|
| 17 |
徐朋刚. 浅议设计单位的造价控制[J]. 能源与节能, 2012 (7): 92- 94.
|
| 18 |
|
| 19 |
|
| 20 |
全超. 光伏电站项目前期工作分析与探讨[J]. 中国高新技术企业, 2016 (12): 185- 186.
|
| 21 |
涂波. 风电项目开发前期工作浅谈[J]. 低碳世界, 2019, 9 (11): 47- 48.
|
| 22 |
李梓芳. 浅谈抽水蓄能电站项目前期工作[J]. 水电与新能源, 2023, 37 (7): 62- 65.
|
| 23 |
|
| 24 |
|
| 25 |
|
| 26 |
|
| 27 |
曾慧娟. 基于伙伴关系的PPP项目绩效评价研究[D]. 重庆: 重庆大学, 2022.
ZENG H J. Research on performance evaluation of PPP project based on partnering[D]. Chongqing: Chongqing University, 2022. (in Chinese)
|
| 28 |
陈佼. 关于做好水利项目前期工作的思考[J]. 中国高新技术企业, 2016 (7): 111- 112.
|
| 29 |
|
| 30 |
|
| 31 |
毛加. EPC项目绩效管理研究[D]. 杭州: 浙江大学, 2013.
MAO J. Research on performance management of EPC project[D]. Hangzhou: Zhejiang University, 2013. (in Chinese)
|
| 32 |
吴丹阳. EPC模式下设计方与施工方合作关系对项目绩效的影响研究[D]. 济南: 山东建筑大学, 2021.
WU D Y. Research on the influence of cooperation between designer and builder on project performance under EPC mode[D]. Jinan: Shandong Jianzhu University, 2021. (in Chinese)
|
| 33 |
|
/
| 〈 |
|
〉 |