Design management of clean energy projects from the perspective of partnering

Yubin ZHAO, Guo LI, Wenzhe TANG

Journal of Tsinghua University(Science and Technology) ›› 2025, Vol. 65 ›› Issue (1) : 115-124.

PDF(1266 KB)
PDF(1266 KB)
Journal of Tsinghua University(Science and Technology) ›› 2025, Vol. 65 ›› Issue (1) : 115-124. DOI: 10.16511/j.cnki.qhdxxb.2024.22.042
Special Section: Construction Management

Design management of clean energy projects from the perspective of partnering

Author information +
History +

Abstract

Objective: Developing clean energy is crucial for achieving China's "double carbon" goals, prompting active investment in clean energy projects across the country. However, these projects face a complex external environment with many stakeholders, which makes large-scale grid integration challenging. Moreover, existing projects often suffer from issues such as insufficient energy allocation regulation, mismatched installed capacity and power demand, low economic efficiency in power transmission, and poor synergy effect among projects, mainly owing to inadequate design management. Although design management is vital in clean energy project management, a lack of research is observed from a collaborative perspective among participants. Methods: This study adopted a mixed research method that combined quantitative research and qualitative research. Quantitative data were obtained through questionnaire surveys, whereas qualitative data were obtained through semistructured interviews and case studies. Respondents included experienced professionals in clean energy project construction, such as owners, designers, suppliers, constructors, and supervisors. Herein, data analysis involved descriptive statistics, mean ranking analysis, difference testing, cluster analysis, and structural equation modeling. Results: The results show that partnering, feasibility studies, and owner's design management positively impact project performance through two paths: (1) partnering → feasibility study → design performance → project performance and (2) partnering → owner's design management → (feasibility study) → design performance → project performance. During the feasibility study, designers should deeply analyze the supply and demand of the clean energy power market, identify internal and cross-regional power consumption objects, and completely master the basic information of the design. They should rationally select sites, strengthen technical scheme demonstrations, fully consider site and surrounding area constraints, reasonably plan project resettlement and environmental protection, and ensure the project's economic feasibility. In the design process, owners should fully understand national and regional energy policies, deepen their understanding of the project objectives and design needs, and guide design development effectively. The contract should specify the design scope, depth, quality, and schedule requirements and reasonably define the responsibilities, rights, and obligations of all parties. It is crucial to establish a sound design management system, prepare a clear design schedule, and dynamically adjust the schedule as required. Implementing a sound design review, change, and optimization process, identifying design risks, and establishing corresponding control mechanisms are also essential. Developing operable design assessment indicators, reasonable reward and punishment measures, and a design interface management mechanism for stakeholders, along with actively applying information technology, is recommended. Combined with a case analysis, this study offers design management suggestions. Conclusions: This study proposes and validates a design management model for clean energy projects, revealing the considerable positive effects and pathways of partnering, feasibility studies, and owner's design management on project performance. Through questionnaires and interviews, this study deeply analyze the current state of the feasibility studies and design management, identifying key issues and factors to focus on in clean energy project design. The results provide theoretical and practical references for managing clean energy project design.

Key words

clean energy projects / partnering / owner's design management / feasibility study

Cite this article

Download Citations
Yubin ZHAO , Guo LI , Wenzhe TANG. Design management of clean energy projects from the perspective of partnering[J]. Journal of Tsinghua University(Science and Technology). 2025, 65(1): 115-124 https://doi.org/10.16511/j.cnki.qhdxxb.2024.22.042

References

1
杨跃斌, 曹路. 南方区域抽水蓄能电站项目前期管理实践[J]. 水电与新能源, 2015 (10): 53-57, 65.
YANG Y B , CAO L . Prophase management practice of pumped storage hydropower stations in southern China[J]. Hydropower and New Energy, 2015 (10): 53-57, 65.
2
钟敏. 水电项目前期规划问题探究[J]. 广东科技, 2012, 21 (11): 102, 110.
ZHONG M . Research on the problems of pre-planning of hydropower projects[J]. Guangdong Science & Technology, 2012, 21 (11): 102, 110.
3
CAIXETA M C B F , FABRICIO M M . A conceptual model for the design process of interventions in healthcare buildings: A method to improve design[J]. Architectural Engineering and Design Management, 2013, 9 (2): 95- 109.
4
ZANELDIN E , HEGAZY T , GRIERSON D . Improving design coordination for building projects. Ⅱ: A collaborative system[J]. Journal of Construction Engineering and Management, 2001, 127 (4): 330- 336.
5
ARDITI D , ELHASSAN A , TOKLU Y C . Constructability analysis in the design firm[J]. Journal of Construction Engineering and Management, 2002, 128 (2): 117- 126.
6
KNOTTEN V , LÆDRE O , HANSEN G K . Building design management: Key success factors[J]. Architectural Engineering and Design Management, 2017, 13 (6): 479- 493.
7
陈云华, 唐文哲, 王继敏, 等. 大型水电EPC项目建设管理创新与实践[M]. 北京: 中国水利水电出版社, 2020.
CHEN Y H , TANG W Z , WANG J M , et al. Construction management innovation and practice of large-scale EPC hydropower projects[M]. Beijing: China Water & Power Press, 2020.
8
余自业, 唐文哲. 数字经济下水利工程建设管理创新与实践[M]. 北京: 清华大学出版社, 2022.
YU Z Y , TANG W Z . Innovation and practice of water conservancy project construction management under digital economy[M]. Beijing: Tsinghua University Press, 2022.
9
朱玉方. 水电项目前期工作研究[J]. 红水河, 2010, 29 (6): 79-84, 94.
ZHU Y F . Study on prophase work of hydropower projects[J]. Hongshui River, 2010, 29 (6): 79-84, 94.
10
李俊华. 浅谈水电项目前期工作管理[J]. 价值工程, 2013, 32 (21): 73- 74.
LI J H . The management of preliminary work of hydropower project[J]. Value Engineering, 2013, 32 (21): 73- 74.
11
JERRARD R , HANDS D , INGRAM J . Design management case studies[M]. London: Routledge, 2002.
12
LOPEZ R , LOVE P E D . Design error costs in construction projects[J]. Journal of Construction Engineering and Management, 2012, 138 (5): 585- 593.
13
李凤新, 张振, 付璇, 等. 浅谈设计管理在项目运行中的重要性及体会[J]. 石化技术, 2016, 23 (2): 260.
LI F X , ZHANG Z , FU X , et al. Discussion on the importance and experience of design management in project operation[J]. Petrochemical Industry Technology, 2016, 23 (2): 260.
14
王胜斌, 缪正建, 武文杰. 全过程工程咨询设计管理实践与绩效评价[J]. 工程技术研究, 2023, 8 (22): 171- 173.
WANG S B , MIAO Z J , WU W J . The design management practice and performance evaluation of whole process engineering consulting[J]. Engineering and Technological Research, 2023, 8 (22): 171- 173.
15
EL REIFI M H , EMMITT S . Perceptions of lean design management[J]. Architectural Engineering and Design Management, 2013, 9 (3): 195- 208.
16
王涛. 工程项目中业主方的设计管理研究: 以连云港项目为例[D]. 北京: 北京建筑大学, 2020.
WANG T. Research on the design management process of the owner of construction projects: Take a project as an example[D]. Beijing: Beijing University of Civil Engineering and Architecture, 2020. (in Chinese)
17
徐朋刚. 浅议设计单位的造价控制[J]. 能源与节能, 2012 (7): 92- 94.
XU P G . Briefly discuss the cost control of design unit[J]. Energy and Energy Conservation, 2012 (7): 92- 94.
18
ZIMINA D , BALLARD G , PASQUIRE C . Target value design: Using collaboration and a lean approach to reduce construction cost[J]. Construction Management and Economics, 2012, 30 (5): 383- 398.
19
KÄRNÄ S , JUNNONEN J M . Designers' performance evaluation in construction projects[J]. Engineering, Construction and Architectural Management, 2017, 24 (1): 154- 169.
20
全超. 光伏电站项目前期工作分析与探讨[J]. 中国高新技术企业, 2016 (12): 185- 186.
QUAN C . Analysis and discussion on the preliminary work of photovoltaic power station project[J]. China High-Tech Enterprises, 2016 (12): 185- 186.
21
涂波. 风电项目开发前期工作浅谈[J]. 低碳世界, 2019, 9 (11): 47- 48.
TU B . Discussion on preliminary work of wind power project development[J]. Low Carbon World, 2019, 9 (11): 47- 48.
22
李梓芳. 浅谈抽水蓄能电站项目前期工作[J]. 水电与新能源, 2023, 37 (7): 62- 65.
LI Z F . On the preliminary work of pumped storage power station projects[J]. Hydropower and New Energy, 2023, 37 (7): 62- 65.
23
TANG W Z , DUFFIELD C F , YOUNG D M . Partnering mechanism in construction: An empirical study on the Chinese construction industry[J]. Journal of Construction Engineering and Management, 2006, 132 (3): 217- 229.
24
DEWULF G , KADEFORS A . Collaboration in public construction: Contractual incentives, partnering schemes and trust[J]. Engineering Project Organization Journal, 2012, 2 (4): 240- 250.
25
LIU Y , TANG W Z , DUFFIELD C F , et al. Improving design by partnering in engineering-procurement-construction (EPC) hydropower projects: A case study of a large-scale hydropower project in China[J]. Water, 2021, 13 (23): 3410.
26
SCOTT B . Partnering in Europe: Incentive based alliancing for projects[M]. London: Thomas Telford, 2001.
27
曾慧娟. 基于伙伴关系的PPP项目绩效评价研究[D]. 重庆: 重庆大学, 2022.
ZENG H J. Research on performance evaluation of PPP project based on partnering[D]. Chongqing: Chongqing University, 2022. (in Chinese)
28
陈佼. 关于做好水利项目前期工作的思考[J]. 中国高新技术企业, 2016 (7): 111- 112.
CHEN J . Thinking about doing the preliminary work of water conservancy project well[J]. China High-Tech Enterprises, 2016 (7): 111- 112.
29
ZHENG T F , QIANG M S , CHEN W C , et al. An externality evaluation model for hydropower projects: A case study of the three gorges project[J]. Energy, 2016, 108, 74- 85.
30
LI X Z , CHEN Z J , FAN X C , et al. Hydropower development situation and prospects in China[J]. Renewable and Sustainable Energy Reviews, 2018, 82, 232- 239.
31
毛加. EPC项目绩效管理研究[D]. 杭州: 浙江大学, 2013.
MAO J. Research on performance management of EPC project[D]. Hangzhou: Zhejiang University, 2013. (in Chinese)
32
吴丹阳. EPC模式下设计方与施工方合作关系对项目绩效的影响研究[D]. 济南: 山东建筑大学, 2021.
WU D Y. Research on the influence of cooperation between designer and builder on project performance under EPC mode[D]. Jinan: Shandong Jianzhu University, 2021. (in Chinese)
33
BASU R . Managing quality in projects: An empirical study[J]. International Journal of Project Management, 2014, 32 (1): 178- 187.