收费公路PPP项目最低收入担保机制设计

  • 刘婷, 王守清, 冯珂
作者信息 +

Minimum revenue guarantee mechanism design for toll road PPP projects

  • LIU Ting, WANG Shouqing, FENG Ke
Author information +
文章历史 +

摘要

该文研究收费公路政府与社会资本合作(public-private partnerships,PPP)项目中最低收入担保机制的设计原则和方法,以改善收入风险的分担。基于文献综述提出了最低收入担保机制设计的5个原则,建立符合以上原则的随机模型以求解最低收入担保机制的收入下限和上限,利用案例展示了所提出方法的应用,并通过数值模拟验证了该方法的有效性。研究表明:根据目标资本结构来确定最低收入担保水平,有助于大幅减小项目公司的破产风险;根据目标投资回报结合竞标的方式来确定超额收入阈值,从而实现超额收入分享,能有效避免企业通过PPP项目获得超额回报。该方法使得最低收入担保与超额收入分享机制对PPP项目财务状况的改善和为政府带来的或有债务可以测算,能为项目方案评审、财务测算和财政承受能力评估等提供量化依据,并改善政府对PPP项目的支付预算管理。

Abstract

This article describes the principles and methodology used to design the minimum revenue guarantee (MRG) mechanism to improve revenue risk allocation for toll road PPP projects. A literature review shows five critical principles for MRG design which are used in a stochastic model to find the optimal upper and lower revenue thresholds. A case study shows the application and effectiveness of this methodology. This research shows that a minimum revenue threshold determined by the target capital structure significantly reduces the bankruptcy probability of the project company. A maximum revenue threshold jointly determined by a target rate of investment return and a bidding process will prevent the private sector from obtaining excessive profits from the PPP project. These method and models will help with quantitative evaluations of the impacts of an MRG on a PPP project's financial status and the government's contingent liabilities to further improve project evaluations and fiscal sustainability assessments as well as budgeting for PPPs.

关键词

政府与社会资本合作(PPP) / 最低收入担保 / 超额收入分享 / 或有债务 / 财政承受能力评价

Key words

public-private partnerships (PPP) / minimum revenue guarantee (MRG) / excess revenue sharing (ERS) / contingent liability / fiscal sustainability assessment

引用本文

导出引用
刘婷, 王守清, 冯珂. 收费公路PPP项目最低收入担保机制设计[J]. 清华大学学报(自然科学版). 2017, 57(6): 661-666 https://doi.org/10.16511/j.cnki.qhdxxb.2017.26.036
LIU Ting, WANG Shouqing, FENG Ke. Minimum revenue guarantee mechanism design for toll road PPP projects[J]. Journal of Tsinghua University(Science and Technology). 2017, 57(6): 661-666 https://doi.org/10.16511/j.cnki.qhdxxb.2017.26.036
中图分类号: F407.9   

参考文献

[1] Guasch J L, Laffont J J, Straub S. Renegotiation of Concession Contracts in Latin America[M]. Washington, DC:World Bank Publication, 2003. [2] Harris C, Hodges J, Schur M. Infrastructure projects:A review of canceled private projects. (2003-01-31). http://siteresources.worldbank.org/EXT_FINANCIAL_S-ECTOR/Resources/282884-1303327122200/252Harri.pdf. [3] Flyvbjerg B, Skamris H M K, Buhl S L. How (in) accurate are demand forecasts in public works projects? The case of transportation[J]. Journal of the American Planning Association, 2005, 71(2):131-146. [4] Chiara N, Garvin M J, Vecer J. Valuing simple multiple-exercise real options in infrastructure projects[J]. Journal of Infrastructure Systems, 2007, 13(2):97-104. [5] Cruz C O, Marques R C. Flexible contracts to cope with uncertainty in public-private partnerships[J]. International Journal of Project Management, 2013, 31(3):473-483. [6] 叶苏东. BOT项目主要风险的管理研究[J]. 项目管理技术, 2008(8):26-31.YE Sudong. Research on major risk management for BOT projects[J]. Project Management Techonology, 2008(8):26-31. (in Chinese) [7] Quiggin J. Public-private partnerships:Options for improved risk allocation[J]. Australian Economic Review, 2005, 38(4):445-450. [8] Xu Y, Yeung J F, Jiang S. Determining appropriate government guarantees for concession contract:Lessons learned from 10 PPP projects in China[J]. International Journal of Strategic Property Management, 2014, 18(4):356-367. [9] Myers S C. Finance theory and financial strategy[J]. Interfaces, 1984, 14(1):126-137. [10] Trigeorgis L, Mason S P. Valuing managerial flexibility[J]. Midland Corporate Finance Journal, 1987, 5(1):14-21. [11] Martins J, Marques R C, Cruz C O. Real options in infrastructure:Revisiting the literature[J]. Journal of Infrastructure Systems, 2013, 21(1), 04014026. [12] 季闯, 袁竞峰, 李启明. 基础设施PPP项目实物期权界定与分析[J]. 工程管理学, 2011, 25(4):393-398.JI Chuang, YUAN Jingfeng, LI Qiming. Definition and analysis of real option in Public Private Partnership projects[J]. Journal of Engineering Management, 2011, 25(4):393-398. (in Chinese). [13] Huang Y L, Chou S P. Valuation of the minimum revenue guarantee and the option to abandon in BOT infrastructure projects[J]. Construction Management and Economics, 2006, 24(4):379-389. [14] Cheah C Y, Liu J. Valuing governmental support in infrastructure projects as real options using Monte Carlo simulation[J]. Construction Management and Economics, 2006, 24(5):545-554. [15] 高峰, 郭菊娥, 王乐, 等. 基于上升敲出期权的基础设施项目政府担保价值研究[J]. 软科学, 2007(4):51-55.GAO Feng, GUO Ju'e, WANG Le, et al. Research on government guarantees value in infrastructure projects based on the up-and-out options[J]. Soft Science, 2007(4):51-55. (in Chinese) [16] 张国兴, 郭菊娥, 龚利. 基础设施项目政府担保价值研究[J].统计与决策, 2007(5):51-52.ZHANG Guoxing, GUO Ju'e, GONG Li. Research on government guarantees value in infrastructure projects[J]. Statistics and Decision, 2007(5):51-52. (in Chinese) [17] Brandao L E, Saraiva E. The option value of government guarantees in infrastructure projects[J]. Construction Management and Economics, 2008, 26(11):1171-1180. [18] Galera A L, Soliño A S. A real options approach for the valuation of highway concessions[J]. Transportation Science, 2010, 44(3):416-427. [19] Jun J. Appraisal of combined agreements in BOT project finance:Focused on minimum revenue guarantee and revenue cap agreements[J]. International Journal of Strategic Property Management, 2010, 14(2):139-155. [20] Ashuri B, Kashani H, Molenaar KR, et al. Risk-neutral pricing approach for evaluating BOT highway projects with government minimum revenue guarantee options[J]. Journal of Construction Engineering and Management, 2011, 138(4):545-557. [21] Iyer K C, Sagheer M. A real options based traffic risk mitigation model for build-operate-transfer highway projects in India[J]. Construction Management and Economics, 2011, 29(8):771-779. [22] Fisher G, Babbar S. Private Financing of Toll Roads[M]. Washington DC:World Bank, 1996. [23] Shan L, Garvin M J, Kumar R. Collar options to manage revenue risks in real toll public-private partnership transportation projects[J]. Construction Management and Economics, 2010, 28(10):1057-1069. [24] Sun Y, Zhang L. Balancing public and private stakeholder interests in BOT concessions:Minimum revenue guarantee and royalty scheme applied to a water treatment project in China[J]. Journal of Construction Engineering and Management, 2014, 141(2):04014070. [25] Ashuri B, Kashani H, Molenaar K R, et al. A valuation model for choosing the optimal minimum revenue guarantee (MRG) in a highway project:A real-option approach[C]//In Construction Research Congress 2010:Innovation for Reshaping Construction Practice. Banff, Alberta, Canada, 2010:8-11. [26] Carbonara N, Costantino N, Pellegrino R. Revenue guarantee in public-private partnerships:A fair risk allocation model[J]. Construction Management and Economics, 2014, 32(4):403-415. [27] Vassallo J, Soliño A. Minimum income guarantee in transportation infrastructure concessions in Chile[J]. Transportation Research Record:Journal of the Transportation Research Board, 2006(1960):15-22. [28] Nombela G, Rus G D. Auctions for infrastructure concessions with demand uncertainty and unknown costs. (2016-05-31). https://mpra.ub.uni-muenchen.de/12023/1/MPRA_paper_12023.pdf.

PDF(1163 KB)

Accesses

Citation

Detail

段落导航
相关文章

/